A can lay a railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in_________?

A. 4

B. 9.6

C. 9

D. 10

Time and Work Mcqs · Easy · 1 month ago

If 10 bulls can plough 20 identical fields in 3 days working 10 hours a day, then in how many days can 30 bulls plough 32 same identical fields working 8 hours a day?

A. 2

B. 8

C. 10

D. 12

Time and Work Mcqs · Easy · 1 month ago

A work can be finished in 16 days by twenty women. The same work can be finished in fifteen days by sixteen men. The ratio between the capacity of a man and a woman is_________?

A. 1:3

B. 4:3

C. 2:3

D. 2:1

Time and Work Mcqs · Easy · 1 month ago

P, Q and R can complete a work in 24, 6 and 12 days respectively. The work will be completed in________days if all of them are working together.

A. 2

B. 3 3⁄7

C. 4 ¼

D. 5

Time and Work Mcqs · Easy · 1 month ago

Two pipes P and Q can fill a cistern in 12 minutes and 16 minutes respectively.  Simultaneously both the pipes are opened together, then after how much time Q should be closed so that the tank is full in 9 min ?

A. 2 min

B. 3 min

C. 4 min

D. 5 min

Time and Work Mcqs · Easy · 1 month ago

A can do a certain job in 12 days. B is 60% more efficient than A. The number of days it takes for B to do the same piece of work, is:_________?

A. 12/6 days

B. 15/2 days

C. 23 days

D. 34 days

Time and Work Mcqs · Easy · 1 month ago

A can do piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?

A. 70 days

B. 120/7 days

C. 50 days

D. 45 days

Time and Work Mcqs · Easy · 1 month ago

A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?

A. 5

B. 6

C. 7

D. 8

Time and Work Mcqs · Easy · 1 month ago